For
any thriving university, the quest for adequate classroom space and dormitory space
is a constant challenge. Indeed, the
history of UNC Greensboro (UNCG) reveals an institution that has had periods of
remarkable growth in its facilities to accommodate a growing student body as
well as new academic programs. In the
1990s, the University was facing a severe space crunch and a need to renovate
some of its existing buildings. In
addition, UNC System administrators were forecasting a rapid growth in school
age applicants in the coming decade.
A
1997 review of UNC Greensboro campus documented the need
for a robust expansion and renovation plan.
The report noted that the most pressing need was the construction of a new
science building. Drawing on these
findings, the University’s administration and science faculty advocated for a new building that would meet the modern research needs of its cutting-edge faculty
and the hands-on learning needs of its student body. This post will examine how the Patricia A. Sullivan
Science Building came to be built.
Prior
to the 1997 facilities study, the UNCG’s science faculty had been discussing for
nearly a decade their need for more classroom spaces, teaching laboratories,
and new equipment to support modern research needs. Science faculty pointed to many of the challenges
of their current home in the Mary Macy Petty Building. At the time of its construction in 1939, the Petty
building and its labs were a model of advanced design. Yet, by the 1990s, science faculty had a long
list of complaints that included poor ventilation systems in the lab areas.
This
decades-long advocacy effort by faculty and administrators helped to raise
awareness amongst the University’s Board of Trustees. Indeed, the Board of Trustees on April 23,
1998 approved the design for a new science laboratory facility. The proposed building was to be located next
to the Eberhart Building along McIver Street.
The Board of Trustees also approved the concept of closing McIver Street
between Carr Street and Walker Ave and turning it into a pedestrian walkway. The landscaped walkway would run the length of
the new science building.
![]() |
| Science Building Drawing |
With
this approved plan in place, UNC Greensboro administrators advocated for this
project and several other projects that were being considered for a state-wide
bond referendum. On November 7, 2000, the
voters of North Carolina passed a $3.1 billion Higher Education Bond Referendum
to fund capital projects for the UNC System schools. As a result of the vote, UNCG was provided
with $160 million to cover the costs of seventeen campus projects. $47.7 million was targeted for the
construction of a 170,000 square foot science building. While the state was providing the funding for
the construction of the building, the University was going to have to spend $5
million on the purchase of equipment for the new building’s laboratories.
On
March 12, 2001, the University held a ground-breaking ceremony. Chancellor Patricia Sullivan presided over
the event that featured the President of the UNC System Phillip Kirk, the chair
of the UNC Board of Governors Ben Ruffin, and UNCG’s own Student Trumpet
Ensemble and Market St. Brass. Sullivan
noted that the “construction of the new science building is UNCG’s number one capital
priority, and largest bond project.” She
added that “it is an essential component in preparing our students to become
viable practitioners of modern science and for building a knowledge base to
support the changing economy of our region.”
The
four-story facility was designed by O’Brien/Atkins Associates of Raleigh, North
Carolina in association with Ellenzweig Associates of Cambridge,
Massachusetts. The building was intended
to house research and instructional space for the Department of Chemistry &
Biochemistry, and instructional space for the Department of Biology. The new building would provide for twenty-five
teaching laboratories, two lecture halls, a 300-seat auditorium, six seminar
rooms, faculty offices, and a 1,500 square-foot teaching greenhouse on the
fourth floor.
The
building project was completed on time.
It was open for classes during the fall 2003 term. The official opening and dedication of the
building took place on October 5, 2003.
Chancellor Sullivan stated that “this new science building is the anchor
point for making this university the principal research center in the Triad by
the end of the century.”
![]() |